Volume 1, Issue 14. May 5, 2008

Welcome to the Pala Raceway Report. We will try and keep you informed of the construction process of the Pala Raceway with regular updates. Also check back for updates on www.palaraceway.com on a regular basis.

Construction Update 5/05/2008:

The mass grading crew is making great progress on the site, as the removal of all the remnants of the mining operation continues. The grading crew continued to use the scrappers to flip the dirt in the lower area of the site and started moving the large gravel pile on the West end of the site. Drainage pipe was delivered to the site as the underground work of storm drains is being started along with the staking of the trenching for the infrastructure that will be getting installed.


Scrappers at work.


Scrapper laying down a row of good dirt.


Galvanized drainage pipes were delivered for the storm drains that are part of the hydrology and drainage plans for the site. It is designed to mitigate the risk of flooding during large storm events.


The lower area of the site.

Warning:
While the mass grading is going on the site is a closed site and no one besides authorized personal will be allowed on site due to the dangerous nature of the construction site. Please do not try and come out to the site, security will not let you through the front gate unless you are chaperoned by a member of the Pala Raceway Staff. Once the mass grading is done and the track building crews are on site we will begin offering site tours.